How long will it take to obtain a temporary building permit if my parcel is outside the fire burned area?

If there are no more than a total of 3 dwelling units on the property and the units will be connected to the County Water and County Sewer, the review time should be approximately 2-3 weeks.

If there are more than a total of 3 dwelling units on the property or the units will not be connected to County Water and County Sewer, the review time may take longer.